Summary of contingencies - Infrastructure Department (French, CSV)
Summary of contingencies - Infrastructure Department: French CSV file you can open as a table, filter, chart and export up to 10,000 rows. From Government and Municipalities of Québec, updated May 2026.
- Format
- CSV
- Access
- Table on demand (prepared when opened)
- Publisher-reported update
- 2026-05-27
Overview of the contingencies of contracts awarded since 2008 in connection with the Water Department and the Infrastructure, Road and Transport Department.
Data overview
- Formats
- CSV
- File languages
- French
- Available actions
- Explore table (prepared automatically) · Access original file
Sample rows
The first 6 rows, as CanQuery read them from the start of the publisher's file on 2026-11-08.
| Année | Pourcentage des travaux contingents | Dépassements de quantité | Imprévus |
|---|---|---|---|
| 2014 | 7,3% | 3,2% | 4,1% |
| 2013 | 7,7% | 4,3% | 3,4% |
| 2011 | N/D | N/D | N/D |
| 2010 | 4,6% | 1,8% | 2,8% |
| 2009 | 7,8% | 3,2% | 4,6% |
| 2008 | 9,9% | 4,4% | 5,5% |