Hearing Order (English, CSV)
Hearing Order: English CSV file you can open as a table, filter, chart and export up to 10,000 rows. From Canada Energy Regulator, updated Jan 2025.
- Format
- CSV
- Access
- Table on demand (prepared when opened)
- Publisher-reported update
- 2025-01-02
Once the Canada Energy Regulator (CER) decides that an application requires a hearing, the CER issues a process letter or a document called a Hearing Order. A Hearing Order usually gives a brief description of the proposed project or application, the list of issues that will be considered, as well as details on the steps in the hearing process and the schedule for the various steps. The Hearing Order includes information on how people might participate in the hearing. The process to apply to participate in a hearing will involve filling in an online form with details such as how the project will impact you or your group.
Data overview
- Formats
- CSV
- File languages
- English
- Available actions
- Explore table (prepared automatically) · Access original file
Sample rows
The first 10 rows, as CanQuery read them from the start of the publisher's file on 2026-11-09. Showing 20 of 21 columns.
| File Number | Hearing Order Number | Issued To Company | English Title | Comments | Total Hearing Days | Intervention Date | Applicant Written Evidence Date | Information Request To Applicant Date | Intervenor Written Evidence Date | Letters Of Comment Date | Oral Statement Date | Information Requests To Intervenor Date | Response To Information Request Date | Reply Evidence Date | Evidentiary Record Closed Date | Hearing Order Date | Commencement Of Hearing Date | Pre Hearing Conference Date | Declaration Of Government Participant Status Date |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6182495 | MH-003-2026 | Trans-Northern Pipelines Inc. | Application for Compensation of Lands and Damages by 9346-5508 Québec inc. against Trans-Northern Pipelines Inc. | 0 | 07/20/2026 | 08/04/2026 | 09/15/2026 | 09/29/2026 | 09/29/2026 | 06/30/2026 | |||||||||
| 6503001 | EH-001-2026 | Powell River Energy Inc. | Application for a 30-year contract-specific electricity export licence | 0 | 04/17/2026 | 05/21/2026 | 07/07/2026 | 08/04/2026 | 11/13/2025 | 08/21/2026 | 09/11/2026 | 10/09/2026 | 04/10/2026 | 11/16/2026 | |||||
| 5689143 | MH-002-2026 | TransCanada PipeLines Limited | Cost apportionment application The Regional Municipality of Peel involving TransCanada PipeLines Limited | 5 | 08/14/2026 | 09/25/2026 | 03/05/2026 | 09/15/2026 | 02/11/2026 | ||||||||||
| 6313824 | MH-001-2026 | Westcoast Energy Inc. | Compensation hearing application from Peace River Greenhouses Ltd. | Compensation hearing application from Peace River Greenhouses Ltd.Westcoast Energy Inc. | 0 | 02/17/2026 | 03/03/2026 | 03/17/2026 | 02/02/2026 | ||||||||||
| 4688859 | MH-004-2025 | Trans Mountain Pipeline ULC | Compensation Hearing Application from Sam Enterprises Ltd. against Trans Mountain Pipeline ULC | 0 | 05/08/2026 | 03/20/2026 | 05/15/2026 | 05/29/2026 | 12/18/2025 | 06/23/2026 | 11/27/2025 | ||||||||
| 6402841 | RH-001-2025 | Enbridge Inc. | AltaGas Ltd. Complaint regarding tolls on the Enbridge Canadian Mainline | 1 | 10/21/2025 | 09/18/2025 | 10/21/2025 | 02/03/2026 | 11/04/2025 | 11/18/2025 | 11/25/2025 | 02/03/2026 | 09/10/2025 | 02/03/2026 | |||||
| 6071165 | MH-003-2025 | NorthRiver Midstream NEBC Connector GP Inc. | NEBC Connector Project - Detailed Route - North Ridge Ventures Ltd. | Statement of opposition of detailed route from Jim Bell re: NEBC Connector Project involving NorthRiver Midstream NEBC Connector GP Inc. | 1 | 07/30/2025 | 08/13/2025 | 08/20/2025 | 07/15/2025 | 08/27/2025 | |||||||||
| 6131431 | MH-002-2025 | Kingston Midstream Westspur Limited | Kingston Midstream Westspur Limited - Application for Leave to Abandon Pipeline 23A and 23B Segments at Pipestone Creek | Written proceeding | 0 | 06/19/2025 | 07/10/2025 | 06/26/2025 | 07/25/2025 | 05/30/2025 | |||||||||
| 6131389 | MH-001-2025 | Trans Mountain Pipeline ULC | Compensation hearing application from Robert Prevost and Nicole Coutts-Prevost - Trans Mountain Pipeline ULC | 2 | 05/16/2025 | 06/09/2025 | 07/09/2025 | 04/11/2025 | 07/08/2025 | 03/18/2025 | |||||||||
| 5073677 | MH-004-2024 | Trans Mountain Pipeline ULC | Application for Compensation of Lands and Damages by Derek Wade Kostiuk against Trans Mountain Pipeline ULC | 0 | 04/04/2025 | 02/25/2025 | 04/09/2025 | 12/05/2024 | 04/22/2025 |